References
GEODIS
Renovation
GUADALAJARA, MEX
Logistics, Logistics warehouse
Industrial lighting
Annual energy savings 748,800 kWh
74 %

Original installation

Original installation ARGIA lighting solution
Type of luminary Fluorescent T5 & T8 luminaires Acuity Brands
Number of luminaires 565 pcs 565 pcs
Total Input 243.30 kW 63.30 kW
Consumption kWh/year 1,012,128 kWh 263,328 kWh
Project resultThe customer‘s total operating costs were reduced by 74% with a significant increase in lighting levels.
Warranty 5 years

ARGIA lighting solution

Type of luminary

Acuity Brands

Number of luminaires 565 ks
Total Input63.3 kW
Consumption kWh/year 263328 kWh
Project resultThe customer‘s total operating costs were reduced by 74% with a significant increase in lighting levels.
Warranty 5 years

Installation parameters:

For GEODIS company we have replaced the already unsuitable lighting of the logistic and warehouse hall with a total area of 13,076 m2 in the Prologis Los Altos Industrial Parks. The installation was carried out without limitation of operation and outdated fluorescent luminaries were replaced by modern dimmable LED luminaries individually controlled with integrated combined daylight and presence sensor. Thanks to ARGIA solution, the customer has achieved an operating cost savings of 74% with a significant increase 50% in the lighting and new lighting in other areas. Everything was delivered on time and in perfect quality.